Quick answer: To install a trench drain in an existing floor, the slab is saw cut along the drain line, the concrete is removed and the trench is excavated. The plumber sets and connects the channel, and the concrete crew pours a concrete surround and restores the floor. The drain's load class must match the traffic that will cross it.
Where are trench drains used in commercial buildings?
Trench drains collect water along a line instead of at a single point. In commercial and industrial buildings they are common in:
Wash bays and vehicle maintenance areas.
Food and beverage processing rooms, where floors are washed down daily.
Loading dock door lines, to stop water reaching the interior floor.
Equipment areas with process water or condensate.
This is not a complete list. Many of these drains are added years after the building was built, when the use of a space changes. That means cutting into a working floor, usually while the rest of the facility keeps running.
Accurate Maintenance Services (AMS) handles the concrete slab cutting, removal and restoration. The plumbing contractor supplies, sets and connects the drain.
How wide and deep does the trench need to be?
The trench has to fit the drain channel plus the concrete surround the manufacturer requires, so it is always wider than the grate. ACO's polymer concrete installation manual sets out the main rules:
Concrete surround: 4,000 psi concrete is recommended.
Surround thickness: typically the same thickness as the slab.
Minimum dimensions: the surround sizes in the manual are minimums. Poor ground or heavy loads need more, and the manual recommends engineering advice for each project.
Heavier classes: above load class C, ACO recommends a full concrete surround.
Trench drains are often sloped, so the trench gets deeper along its run. The plumbing drawings should give the channel's start and end elevations and the outlet location, so the concrete crew can lay out the cut correctly. Check the existing slab thickness too. If the trench comes close to a footing or runs through an elevated slab, get an engineer's input before cutting.
What is the trench drain installation sequence?
The work follows the same order on most jobs:
Lay out and locate. Mark the drain line, trench width and outlet route. Check drawings and scan for embedded items such as conduit or reinforcement. See concrete scanning before cutting or coring for what scanning can and cannot find.
Saw cut the edges. Straight, full-depth cuts give clean edges for the new concrete. Our commercial concrete slab cutting guide covers saws and cutting depths.
Remove concrete and excavate. Break out the slab between the cuts, haul it away and dig to the required depth without undermining the slab on either side.
Set the drain. The plumber places the channel to line and level, secures it against floating during the pour and connects the outlet.
Pour the surround. The concrete crew places reinforcement where specified, pours the surround and finishes it about 1/8 inch above the grate, as ACO's manual specifies, so water flows into the channel.
Cure and reopen. Keep traffic off until the concrete has reached the strength the design calls for, then install the grates and reopen the area.
Agree before the pour who inspects the channel position and connections, because once the concrete is placed they cannot be adjusted.
What load class does a warehouse trench drain need?
Trench drains are rated by load class under EN 1433, the European standard for drainage channels. US manufacturers such as ACO use it too. ACO's commercial trench drain range lists these classes:
Class A: 3,372 lb test load. Pedestrian areas.
Class B: 28,101 lb. Car parks and light vehicles.
Class C: 56,202 lb. Slow-moving commercial vehicles.
Class E: 134,885 lb. Areas with high wheel loads, such as industrial yards and forklift traffic.
Class F: 202,328 lb. Particularly high wheel loads, such as airport pavements.
Class D, for roads, completes the set of six classes in EN 1433. A drain that loaded forklifts or trucks cross needs a heavy-duty class, with a locked grate. Give the supplier the weight of your loaded forklifts, wheel type and how often they cross, and let them confirm the class in writing. A heavy grate does not help if the concrete around the channel is too thin to carry the load.
How do you stop the concrete beside the drain from cracking?
Cracks along a new trench usually come from weak support or poor joint details. To prevent them:
Compact the base under the surround before the pour.
Cut back broken concrete at the trench edges until you reach sound slab.
Plan the joints. The designer decides where the new concrete ties into the old slab with dowels and where a joint is left free to move. Narrow slivers of old concrete between the trench and an existing joint should be removed.
Match the slab thickness so the surround is not a thin, weak strip.
At exterior dock doors, the water problem may extend beyond the drain line. Our article on how poor drainage damages loading dock areas explains what standing water does to dock concrete. If the approach slab itself is broken, plan the drain together with loading dock approach and ramp repair.
Can the facility stay open during the work?
Yes, in most cases. The trench area is closed off and the rest of the floor stays in use. The plan should cover:
Barricades around open trenches, and steel plates designed for the traffic if vehicles must cross before the pour.
Dust control. Wet cutting or vacuum extraction keeps silica dust down, as required under OSHA's respirable crystalline silica standard for construction, 29 CFR 1926.1153.
Slurry control, so cutting water does not run into working areas or existing drains.
Phasing long drain runs in sections, so aisles and doors reopen as each section is finished.
What goes in the concrete and plumbing scopes?
Clear scopes stop gaps between the two trades. A typical split:
Concrete contractor: layout of cuts, saw cutting, removal and disposal, excavation, base preparation, reinforcement, concrete surround, floor finish and cleanup.
Plumbing contractor: drain design and sizing, channel and grate supply, setting the channel, outlet and pipe connections, and testing.
Owner or general contractor: scanning, permits, design approvals and inspections, plus any floor coating that has to be reinstated around the new drain.
Frequently asked questions
Can you install a trench drain in existing concrete?
Yes. The slab is saw cut and removed along the drain line, the plumber sets the channel and the concrete is rebuilt around it with a concrete surround.
How wide is the trench for a trench drain?
It depends on the channel size and the surround the manufacturer requires. The trench is always wider than the grate, and the surround is typically as thick as the existing slab.
What load class do I need for forklift traffic?
Areas with high wheel loads, such as forklift traffic, often call for EN 1433 Class E, and the heaviest loads for Class F. The drain supplier should confirm the class for your actual equipment.
Who installs the trench drain itself?
The plumbing contractor supplies, sets and connects the drain. The concrete contractor cuts and removes the slab and pours the surround and floor around it.
How AMS can help
AMS cuts trenches for drains, plumbing and utilities in commercial floors across New Jersey and Eastern Pennsylvania, and restores the concrete once the drain is set. We coordinate with your plumber, control dust and slurry and clean up fully after the job. For round penetrations, see our concrete core drilling service.